Thursday, May 3, 2012

We're floored!

PM said that the flooring guys had an opening and if we wanted them to move forward a week early and we agreed, but specified that the floor had to be 100% covered to keep it from getting damaged and it was with a thick foam type layer. Waiting for tile backsplash, carpet, staircase stain, driveway (been too rainy) & the punch list drill down to be completed which mainly consists of drywall & trim touch up. It looks like the gas line people hit some water pvc pipe that will now need to be replaced and will delay the sod...booo! --Ericka




Tuesday, May 1, 2012

Tuesday 5/1

Had some off and on rain so that kept the driveway from being done, but that didnt stop the deck/garage stairs, irrigation people, columns and coach lights from going up. The PM is waiting until the last week to do the flooring, which is a great idea.

Wasnt expecting a recessed light here but we like the clean look so...score!
My first (or so) job is to customize this guy (12x14) with a cedar stain, lights, and a siding matched accent color
Something like this but with a darker stain


The stone patio probably wont be done until next year, too many other things to handle
Irrigation Control
Irrigation Zone Connections
Here is the opener RH installs. I see a lot of people talking about quiet belt-driven openers. 
This one is chain driven and isnt that noisy. Why wouldnt I want to hear my garage opening anyway?



default thermostat, not sure how programmable this one is, but will definitely change it out if its not flexible